понедельник, 20 января 2020 г.

6.6 Control Schedule

It is the process of monitoring the status of the project to update the project schedule and managing changes to the schedule baseline.

The key benefit: the schedule baseline is maintained throughout the project.

Frequency: throughout the project.


Process/ Assets GroupInputThe processOutputProcess / Assets Group
Project Management PlanSchedule management plan6.6 Control ScheduleWork performance information4.5 Monitor and Control Project Work
Schedule baselineChange Request4.6 Perform Integrated Change Control
Scope baselineSchedule management planProject Management Plan
Performance measurement baselineSchedule baseline
Project DocumentsLesson learned registerCost baseline
Project calendarsPerformance measurement baseline
Project scheduleSchedule forecastProject Documents
Resource calendarsAssumption log
Schedule dataBasis of estimates
4.3 Direct and Manage Project WorkWork performance dataLesson learned register
Enterprise / OrganizationOrganizational process assetsProject schedule
Resource calendars
Risk register
Schedule data

The process concerns with:

  • Determining the current status of the project schedule,
  • Influencing the factors that create schedule changes,
  • Reconsidering necessary schedule reserves,
  • Determining if the project schedule has changed,
  • Managing the actual changes as they occur.

For agile approach:

  • Determining the current status of the project schedule by comparing the total amount of work delivered and accepted against the estimates of work completed for the elapsed time cycle;
  • Conducting retrospectives for correcting processes and improving, if required;
  • Reprioritizing the remaining work plan (backlog);
  • Determining the rate at which the deliverables are produced, validated, and accepted (velocity) in the given time per iteration;
  • Determining that the project schedule has changed;
  • Managing the actual changes as they occur.

For contractual work the milestones are controlled. Scheduled status reviews and walkthroughs should be done to verify the contractor reports.

6.6.1 Inputs


6.6.1.1 Project Management Plan


Includes:

  • Schedule management plan. Frequency to update, reserve usage, how to control;
  • Schedule baseline. To compare actual with baseline.
  • Scope baseline.
  • Performance measurement baseline.

6.6.1.2 Project Documents


Include:

  • Lesson learned register.
  • Project calendars.
  • Project schedule.
  • Resource calendars.
  • Schedule data.

6.6.1.3 Work Performance Data


  • Started activities;
  • Actual duration;
  • Remaining duration;
  • Physical percent complete;
  • Completed activities.

6.6.

6.6.1.4 Organizational Process Assets


Include:

  • Existing formal/informal schedule control-related policies, procedures, guidelines;
  • Schedule control tools;
  • Monitoring and reporting methods to be used.

6.6.2 Tools and Techniques


6.6.2.1 Data Analysis


Includes:

  • Earned value analysis. To assess the magnitude of variation to the original schedule baseline;
  • Iteration burndown chart. To track the work remaining to be completed in the iteration backlog. Variance with an ideal burndown (diagonal line) is analyzed. A forecast trend line is used to predict the likely variance at iteration completion.



  • Performance reviews. To measure, compare, analyze schedule performance against the baseline: actual start and finish dates, percent complete, remaining duration for work in progress.
  • Trend analysis. To analyze performance over time.
  • Variance analysis. Analysis of variances in planned values versus actual for start/finish dates, duration, float. Also cause, degree, future implications.
  • What-if scenario analysis.

6.6.2.2 Critical Path Method


Progress along the critical path -> schedule status.

6.6.2.3 Project Management Information System (PMIS)


Track planned dates versus actual dates.

6.6.2.4 Resource Optimization


6.6.2.5 Leads and Lags


Adjusting leads and lags to find way to bring project activities into alignment with the plan.

6.6.2.6 Schedule Compression


6.6.3 Outputs


6.6.3.1 Work Performance Information


6.6.3.2 Schedule Forecasts


  • Earned value performance indicators,
  • Schedule reserve information.

6.6.3.3 Change Requests


Schedule variance analysis/progress reports reviews/performance measures/modification of the project scope/modification of project schedule => change requests.

6.6.3.4 Project Management Plan Updates


Includes:

  • Schedule management plan.
  • Schedule baseline. Changes in project scope, resources, activity duration, results of schedule compression, performance issues.
  • Cost baseline.
  • Performance measurement baseline.

6.6.3.5 Project Documents Updates


Include:

  • Assumption log.
  • Basis of estimates.
  • Lesson learned register.
  • Project schedule.
  • Resource calendars.
  • Risk register.
  • Schedule data.

Комментариев нет:

Отправить комментарий