Description: the process of estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work. The process is very close to the process Estimate Cost.
Key benefit: it identifies the type, quantity, and characteristics of resources required to complete the project.
Frequency: periodically throughout the project as needed.
Include:
Include:
In team and physical resource planning and estimating.
An algorithm or a statistical relationship between historical data and other variables to calculate resource quantities needed for an activity.
Alternatives analysis. Various levels of resource capability or skills, different sizes or types of machines, different tools (manual versus automated), and make-rent-or-buy decisions.
Planning meetings with functional managers to estimate the resources needed per activity, level of effort (LoE), skill level of the team resources, and the quantity of the materials needed. Participants at these meetings may include the project manager, the project sponsor, selected project team members, selected stakeholders, and others.
The types and quantities of resources required for each work package or activity in a work package and can be aggregated to determine the estimated resources for each work package, each WBS branch, and the project as a whole.
A hierarchical representation of resources by category and type.
Resource categories
Types:
Key benefit: it identifies the type, quantity, and characteristics of resources required to complete the project.
Frequency: periodically throughout the project as needed.
Process/ Asset Group | Input | The Process | Output | Process/ Asset Group |
---|---|---|---|---|
Project Management Plan | Resource management plan | 9.2 Estimate Activity Resources | Resource requirements | Project Documents |
Scope baseline | Basis of estimate | |||
Project Documents | Activity attributes | Resource breakdown structure | ||
Activity list | Activity attributes | |||
Assumption log | Assumption log | |||
Cost estimate | Lesson learned register | |||
Resource calendars | ||||
Risk register | ||||
Enterprise/ Organization | Enterprise environmental factors | |||
Organizational process assets |
9.2.1 Inputs
9.2.1.1 Project Management Plan
Include:
- Resource management plan. The approach to identify the different resources needed for the project, the methods to quantify the resources needed for each activity and aggregates this information.
- Scope baseline. The project and product scope necessary to meet the project objectives.
9.2.1.2 Project Documents
- Activity attributes. The primary data source for use in estimating team and physical resources.
- Activity list.
- Assumption log. Information on productivity factors, availability, cost estimates, and approaches to work.
- Cost estimates.
- Resource calendars. The working days, shifts, start and end of normal business hours, weekends, and public holidays when each specific resource is available.
- Risk register. The individual risks that can impact resource selection and availability.
9.2.1.3 Enterprise Environmental Factors
Include:
- Resource location,
- Resource availability,
- Team resource skills,
- Organizational culture,
- Published estimating data, and
- Marketplace conditions.
9.2.1.4 Organizational Process Assets
- Policies and procedures regarding staffing,
- Policies and procedures relating to supplies and equipment, and
- Historical information regarding types of resources used for similar work on previous projects.
9.2.2 Tools and Techniques
9.2.2.1 Expert Judgement
In team and physical resource planning and estimating.
9.2.2.2 Bottom-up Estimating
9.2.2.3 Analogous Estimating
9.2.2.4 Parametric Estimating
An algorithm or a statistical relationship between historical data and other variables to calculate resource quantities needed for an activity.
9.2.2.5 Data Analysis
Alternatives analysis. Various levels of resource capability or skills, different sizes or types of machines, different tools (manual versus automated), and make-rent-or-buy decisions.
9.2.2.6 Project Management Information System (PMIS)
9.2.2.7 Meetings
Planning meetings with functional managers to estimate the resources needed per activity, level of effort (LoE), skill level of the team resources, and the quantity of the materials needed. Participants at these meetings may include the project manager, the project sponsor, selected project team members, selected stakeholders, and others.
9.2.3 Outputs
9.2.3.1 Resource Requirements
The types and quantities of resources required for each work package or activity in a work package and can be aggregated to determine the estimated resources for each work package, each WBS branch, and the project as a whole.
9.2.3.2 Basis of Estimates
- Method used to develop the estimate,
- Resources used to develop the estimate (such as information from previous similar projects),
- Assumptions associated with the estimate,
- Known constraints,
- Range of estimates,
- Confidence level of the estimate, and
- Documentation of identified risks influencing the estimate.
9.2.3.3 Resource Breakdown Structure
A hierarchical representation of resources by category and type.
Resource categories
- Labor,
- Material,
- Equipment, and
- Supplies.
Types:
- Skill level,
- Grade level,
- Required certifications, or
- Other
9.2.3.4 Project Documents Updates
- Activity attributes.
- Assumption log. Assumptions regarding the types and quantities of resources required.
- Lessons learned register.
Комментариев нет:
Отправить комментарий