Estimating task or project status very difficult.
Budgeted expenditures or baseline expenditures.
Earned value of work performed - value completed.
There are several conventions to aid in estimating percent completion:
The before mentioned variants can be applied to tasks not to the project itself. It the project include a lot of tasks then any of the variant applied is good enough.
The concept of earned value balances planned (baseline) cost, actual cost, schedule.
Cost (spending) variance (CV): EV - AC. Or money budgeted to accomplish the work done on current point of time minus actual cost of this work.
The schedule variance (SV) = EV - PV. Or budgeted money for the work done minus budgeted money to be spend on the work to be done on the current time.
The time variance (TV) = ST - AT. Or planned time minus actual time.
Variances can be calculated as ratios or indexes.
Cost Performance Index (CPI) = EV/AC
Schedule Performance Index (SPI) = EV/PV
Time Performance Index (TPI) = ST/AT. It is useful when an organization wishes to compare the performance of several projects. But be careful on the degree of accuracy of calculation of percent complete.
Example:
On current moment the work is expected to be costed as of 1500. The actual expenses are 1350. The completion percent = 67%.
Variances:
Cost Variance = EV - AC = 1500 * .67 - 1350 = - 350
Schedule Variance = EV - PV = 1500 * 0.67 - 1500 = -500.
Cost performance index CPI = EV / AC = 1500*0.67/1350 = 0.74
SPI = EV / PV = 1500 * 0.67 / 1500 = 0.67.
Time scheduled ST = AT * EV / PV.
Time variance TV = AT * (SPI - 1)
Cost Schedule Index CSI = CPI * SPI = EV ^ 2/ AC / PV.
If the project will continue with current rate of expenses then
Estimated cost to complete ETC = (BAC - EV) / CPI = (1500 - 1000) / 0.74 = 676
Estimated cost at completion EAC = ETC + AC = 676 + 1000 = 2026
Budgeted expenditures or baseline expenditures.
Earned value of work performed - value completed.
There are several conventions to aid in estimating percent completion:
- 50/50 rule. 50% completion is assumed when the task is begun, remaining 50% - when the work is complete. It is excessively generous for the task beginning and conservative toward the end of the task.
- 0/100 rule. Very conservative rule. The project always seems to be running late. The earned value line will always lag the planned value line.
- Critical input use rule. Task progress is defined by the amount of a critical inputs. Amount of poured concrete cubic meters -> status of the task of building the foundation.
- The proportionality rule. Uses time or cost as the critical input.
The before mentioned variants can be applied to tasks not to the project itself. It the project include a lot of tasks then any of the variant applied is good enough.
The concept of earned value balances planned (baseline) cost, actual cost, schedule.
- Budget at Completion (BAC).
- Estimated cost at completion (EAC).
Cost (spending) variance (CV): EV - AC. Or money budgeted to accomplish the work done on current point of time minus actual cost of this work.
The schedule variance (SV) = EV - PV. Or budgeted money for the work done minus budgeted money to be spend on the work to be done on the current time.
The time variance (TV) = ST - AT. Or planned time minus actual time.
Variances can be calculated as ratios or indexes.
Cost Performance Index (CPI) = EV/AC
Schedule Performance Index (SPI) = EV/PV
Time Performance Index (TPI) = ST/AT. It is useful when an organization wishes to compare the performance of several projects. But be careful on the degree of accuracy of calculation of percent complete.
Example:
On current moment the work is expected to be costed as of 1500. The actual expenses are 1350. The completion percent = 67%.
Variances:
Cost Variance = EV - AC = 1500 * .67 - 1350 = - 350
Schedule Variance = EV - PV = 1500 * 0.67 - 1500 = -500.
Cost performance index CPI = EV / AC = 1500*0.67/1350 = 0.74
SPI = EV / PV = 1500 * 0.67 / 1500 = 0.67.
Time scheduled ST = AT * EV / PV.
Time variance TV = AT * (SPI - 1)
Cost Schedule Index CSI = CPI * SPI = EV ^ 2/ AC / PV.
If the project will continue with current rate of expenses then
Estimated cost to complete ETC = (BAC - EV) / CPI = (1500 - 1000) / 0.74 = 676
Estimated cost at completion EAC = ETC + AC = 676 + 1000 = 2026
Комментариев нет:
Отправить комментарий