8.3 Control Quality

Description: the process of monitoring and recording results of executing the quality management activities in order to assess performance and ensure the project outputs are complete, correct and meet customer expectations. It determines if the project outputs do what they were intended to do. Those outputs need to comply with all applicable standards, requirements, regulations, and specifications. The process is performed to measure the completeness, compliance, and fitness for use of a product or service prior to user acceptance and final delivery. It is done by measuring all steps, attributes, and variables.

Key benefit: verifying that project deliverables and work meet the requirements specified by key stakeholders for final acceptance.

Frequency: throughout the project.


Process / Asset GroupInputThe processOutputProcess / Asset Group
Project Management PlanQuality management plan8.3 Control QualityWork performance information4.5 Monitor and Control Project Work
Project DocumentsLesson learned registerChange requests4.6 Perform Integrated Change Control
Quality metricsVerified Deliverables5.5 Validate Scope
Test and evaluation documentsQuality management planProject Management Plan
4.3 Direct and Manage Project WorkDeliverablesQuality control measurementsProject Documents
Work performance dataIssue log
4.6 Perform Integrated Change ControlApproved change requestsLesson learned register
Enterprise / OrganizationEnterprise environmental FactorsRisk register
Organizational Process assetsTest and evaluate documents

8.3.1 Inputs


8.3.1.1 Project Management Plan


Quality management plan: how quality control will be performed.

8.3.1.2 Project Documents


Include:

  • Lesson learned register.
  • Quality metrics. Project/product attributes and how compliance will be verified to them.
  • Test and evaluation documents.

8.3.1.3 Approved Change Requests


May include modifications such as

  • Defect repairs,
  • Revised work methods,
  • Revised schedules.

8.3.1.4 Deliverables


Any unique and verifiable product, result, capability to perform a service that is required to be produced to complete a process, phase, project.

8.3.1.5 Work Performance Data


Data on product status such as observation, quality metrics, measurements for technical performance, project quality performance, cost performance.

8.3.1.6 Enterprise Environmental Factors


Include:

  • Project management informational system.
  • Government agency regulations.
  • Rules, standards, guidelines.

8.3.1.7 Organizational Process Assets


Include:

  • Quality standards and policies;
  • Quality templates:
    • Check sheets,
    • Check lists,
    • Others.
  • Issue and defect reporting procedures and communication policies.

8.3.2 Tools and Techniques


8.3.2.1 Data Gathering


Include:

  • Checklists.
  • Check sheets.
  • Statistical sampling. Inspection of the part of the population.
  • Questionnaires and Surveys. Customer satisfaction after the deployment.



8.3.2.2 Data Analysis


Include:

  • Performance review.
  • Root cause analysis (RCA).

8.3.2.3 Inspection


The examination of a work product to determine if it conform to documented standards. Include measurements. May be called:

  • Reviews,
  • Peer reviews,
  • Audits,
  • Walkthroughs.

8.3.2.4 Testing/Product Evaluations


The intent of testing is to find errors, defects, bugs, or other non-conformance problems. The type, amount, and extent of tests needed to evaluate each requirement are part of the project quality plan and depend on the nature of the project, time, budget, and other constraints. Tests can be performed throughout the project, as different components of the project become available, and at the end of the project on the final deliverables. Early testing helps identify non-conformance problems and helps reduce the cost of fixing the nonconforming components.

8.3.2.5 Data Representation


  • Cause-and-effect diagrams.
  • Control charts. To determine whether or not a process is stable or has predictable performance. Upper and lower level limits. The control limits are determined using standard statistical calculations and principles to ultimately establish the natural capability for a stable process.
  • Histograms.
  • Scatter diagrams.

8.3.2.6 Meetings


  • Approved change requests review.
  • Retrospectives/lesson learned.
    • Successful elements in the project/phase,
    • What could be improved,
    • What to incorporate in the ongoing project and what in future project,
    • What to add to the organization process assets.

8.3.3 Outputs


8.3.3.1 Quality Control Measurements


The documented results of Control Quality activities.

8.3.3.2 Verified Deliverables


8.3.3.3 Work Performance Information


  • Project requirements fulfillment,
  • Causes for rejections,
  • Rework required,
  • Recommendations for corrective actions,
  • Lists of verified deliverables,
  • Status of the quality metrics,
  • The need for process adjustments.

8.3.3.4 Change Requests


8.3.3.5 Project Management Plan Updates


The organization's change control process via a change request.

8.3.3.6 Project Documents Updates


Include:

  • Issue log.
  • Lesson learned register.
  • Risk register.
  • Test and evaluation documents.

вторник, 11 февраля 2020 г.

8.2 Manage Quality

Description: It is the process of translating the quality management plan into executable quality activities that incorporate the organization's quality policy into the project. It uses data and results from the Control Quality process to reflect overall quality status of the project to the stakeholders. Sometimes called quality assurance but Manage Quality has a broader definition than quality assurance. In project management quality assurance is on the processes used in the project. Quality Assurance is about using project processes effectively: assure stakeholder that the final product will meet their needs, expectations, requirements.

Manage Quality includes all the quality assurance activities + the product design aspects and process improvements. It implements a set of planned and systematic acts and processes defined withing the project's quality management plan that helps to:

  • Design an optimal and mature product by implementing specific design guidelines that address specific aspects of the products,
  • Build confidence that a future output will be completed in a manner that meets the specified requirements and expectations throughout quality assurance tools and techniques (quality audit and failure analysis),
  • Confirm that the quality processes are used and the their use meets the quality objectives of the project,
  • Improve the efficiency and effectiveness of processes and activities to achieve better results and performance and enhance stakeholders' satisfaction.

The organization's quality assurance department may be used to execute some organizational functions. Manage Quality is considered the work of everybody.

Key benefit: it increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality.

Frequency: throughout the project.

Process / Asset GroupInputThe ProcessOutputProcess / Asset Group
Project Management PlanQuality management plan8.2 Manage QualityChange requests4.6 Perform Integrated Change Control
Project DocumentsLesson learned registerQuality management planProject Management Plan
Quality control measurementsScope baseline
Quality metricsSchedule baseline
Risk reportCost baseline
Enterprise / OrganizationOrganizational process assetsQuality reportsProject documents
Test and evaluation documents
Issue log
Lesson learned register
Risk register

8.2.1 Inputs


8.2.1.1 Project Management Plan


Quality management plan: the acceptable level of project and product quality, how to ensure this level, what to do with nonconforming products, what corrective action to implement.

8.2.1.2 Project Documents


Include:

  • Lesson learned register.
  • Quality control measurements. Used to analyze and evaluate the quality of the processes and deliverables of the project against the standard of the performing organization or the specified requirements. Also used to evaluate the measurements itself.
  • Quality metrics. The metrics are verified itself. They are used as a basis for the development of test scenarios for the project and its deliverables and for improvement initiatives.
  • Risk reports. Used to identify sources of overall project risk.

8.2.1.3 Organizational Process Assets


Assets list:

  • Organizational quality management system: policies, procedures, and guidelines;
  • Quality templates: check sheets, traceability matrix, test plan, test documents, others;
  • Results from previous audits;
  • Lesson learned register.

8.2.2 Tools and Techniques


8.2.2.1 Data Gathering


Checklist: a structural tool, component-specific, used to verify that a set of required steps has been performed or to check if a list of requirements has been satisfied.

8.2.2.2 Data Analysis


Include:

  • Alternatives analysis.
  • Document analysis.
  • Process analysis.
  • Root cause analysis (RCA).

8.2.2.3 Decision Making


Multicriteria decision making: evaluation of several criteria when discussing alternatives that impact project or product quality. Project decision: choosing between different implementation scenarios or suppliers. Product decision: evaluating the life cycle cost, schedule, stakeholder satisfaction, risks.

8.2.2.4 Data Representation


Include:

  • Affinity diagrams. To organize potential causes of defects into groups to show areas to be focused on the most.
  • Cause-and-effect /Fishbone diagrams. It breaks down the causes of the problem statement identified into discrete branches to identify the main/root cause of the problem.
  • Flowcharts. A series of steps that lead to a defect.
  • Histograms.
  • Matrix diagrams. Factor-objective relations.
  • Scatter diagrams. Relations between two variables.

8.2.2.5 Audits


A structured, independent process to determine project compliance with organizational/project policies, processes, procedures. Usually conducted by a external team. Quality audit objectives:

  • Identifying all good/best practices;
  • Identifying all nonconformity, gaps, and shortcoming;
  • Sharing good practices;
  • Proactively offering assistance in a positive manner to improve the implementation of processes -> help to raise team productivity;
  • Highlighting contribution of each audit in the lessons learned repository of the organization.

Quality audit can confirm the implementation of approved change requests.

8.2.2.6 Design for X


DfX - a set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect of the design. DfX can control or even improve the product's final characteristics.

8.2.2.7 Problem Solving


It can include gathering additional information, critical thinking, creative, quantitative, logical approaches:

  • Defining the problem;
  • Identifying the root cause;
  • Generate possible solutions;
  • Choosing the best solution;
  • Implementing the solution;
  • Verifying solution effectiveness.

8.2.2.8 Quality Improvement Methods


Plan-Do-Check-Act, Six Sigma.

8.2.3 Outputs


8.2.3.1 Quality Reports


Can be graphical, numerical, qualitative. They are used by other departments. May include:

  • Quality management issues escalated by the team;
  • Recommendations for process, project, product improvements;
  • Corrective actions recommendations;
  • Summary.

8.2.3.2 Test and Evaluation Documents


Dedicated checklists, detailed requirements traceability matrices.

8.2.3.3 Change Requests


8.2.3.4 Project Management Plan Updates


Components that may requires a change request:

  • Quality management plan.
  • Scope baseline.
  • Schedule baseline.
  • Cost baseline.

8.2.3.5 Project Document Updates


  • Issue log.
  • Lesson learned register.
  • Risk register.

понедельник, 10 февраля 2020 г.

8.1 Plan Quality Management

Definition: the process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards.

Key benefit: it provides guidance and direction on how quality will be managed and verified throughout the project.

Frequency: once or at predefined points in the project.


Process/ Asset GroupInputThe ProcessOutputsProcess/ Asset Group
4.1 Develop Project CharterProject Charter8.1 Plan Quality ManagementQuality management planProject Management Plan
Project Management PlanRequirements management planRisk management plan
Risk management planScope baseline
Stakeholder management planQuality metricsProject documents
Scope baselineLesson learned register
Project DocumentsAssumption logRequirements traceability matrix
Requirements documentationRisk register
Requirements traceability matrixStakeholder register
Risk register
Stakeholder register
Enterprise/ OrganizationEnterprise environment factors
Organizational process assets

8.1.1 Inputs


8.1.1.1 Project Charter


It provides high-level project description and product characteristics, approval requirements, project objectives, related success criteria.

8.1.1.2 Project Management Plan


  • Requirements management plan. The approach for identifying, analyzing, and managing the requirements that the quality management plan and quality metrics will reference.
  • Risk management plan. The approach for identifying, analyzing, and monitoring risks.
  • Stakeholder engagement plan. The method for documenting the stakeholders' needs and expectations.
  • Scope baseline. WBS -> for which objects quality management + the acceptance criteria.

8.1.1.3 Project Documents


  • Assumption log. For quality requirements.
  • Requirements documentation. Captures the requirements for the project and deliverables.
  • Requirements traceability matrix. It links product requirements to deliverables -> ensure each requirement is tested.
  • Risk register. It contains information on threats and opportunities.
  • Stakeholder register. It helps to identify stakeholders who have a particular interest/impact on quality.

8.1.1.4 Enterprise Environmental Factors


Includes:

  • Governmental agency regulations;
  • Rules, standards, and guidance specific to the application area;
  • Geographic distribution;
  • Organizational structure;
  • Marketplace conditions;
  • Working or operating conditions of the project or its deliverables;
  • Cultural perceptions.

8.1.1.5 Organizational Process Assets


Includes:

  • Organizational quality management system:
    • Policies;
    • Procedures;
    • Guidelines;
  • Quality templates such as check sheets, traceability matrix, others;
  • Historical databases and lesson learned repository.

8.1.2 Tools and Techniques


8.1.2.1 Expert Judgement


Topics:

  • Quality assurance;
  • Quality control;
  • Quality measurements;
  • Quality improvements;
  • Quality systems.

8.1.2.2 Data Gathering


Includes:

  • Benchmarking. Comparing actual or planned project practices or the project quality standards to identify best practices, generate ideas for improvements, and provide a basis for measuring performance.
  • Brainstorming. To gather data creatively from a group of team members or subject matter experts to develop the quality management plan.
  • Interviews. To gather project and product quality needs and expectations, implicit and explicit, formal or informal.

8.1.2.3 Data Analysis


Include:

  • Cost-benefit analysis. A financial analysis tool to estimate the strengths and weakness of alternatives in order to determine the best alternative. To determine if the planned quality activities are cost effective.
  • Cost of quality COQ.
    • Prevention costs.
    • Appraisal costs. Costs related to evaluating, measuring, auditing, and testing.
    • Failure costs (internal/external).



8.1.2.4 Decision Making


Multicriteria decision analysis to identify the key issues and suitable alternatives to be prioritized as a set of decisions for implementation. Criteria are prioritized and weighed before being applied to all available alternatives to obtain a mathematical score for each alternative. The alternatives are then ranked by score.

8.1.2.5 Data Representation


  • Flowcharts. The sequence of steps.
  • Logical data models.
  • Matrix diagrams.
  • Mind mapping.

8.1.2.6 Test and Inspection Planning


The tests and inspections are industry dependent. Identify how to test/inspect the product, deliverables, how to meet the goal for the product's performance and reliability.

8.1.2.7 Meetings


8.1.3 Outputs


8.1.3.1 Quality Management Plan


It describes how applicable policies, procedures, guidelines will be implemented. Activities and resources for the project to achieve the quality objectives.

Formal/informal, detailed/broadly framed.

It should be reviewed early to ensure that decisions are based on accurate information.

Components:

  • Quality standards that will be used by the project.
  • Quality objectives;
  • Quality roles and responsibility;
  • Project deliverables and processes subject to quality review;
  • Quality control and quality management activities planned for the project;
  • Quality tools that will be used;
  • Major procedures relevant for the project.

8.1.3.2 Quality Metrics


It specifically describes a project or product attribute and how the Control Quality will verify compliance to it (failure rate, number of defects, ...)

8.1.3.3 Project Management Plan Updates


Change control process.

Components:

  • Risk management plan. Decisions on quality -> risks.
  • Scope baseline. Quality management activities -> scope of work.

8.1.3.4 Project Documents Updates


  • Lesson learned register.
  • Requirements traceability matrix.
  • Risk register.
  • Stakeholder register.

вторник, 4 февраля 2020 г.

8 Project Quality Management

Includes the progress for incorporating the organization's quality policy regarding planning, management, and controlling project and product quality requirements in order to meet stakeholder's objectives.


Key Concepts for Project Quality Management

Quality and grade are not the same concepts. Quality as a delivered performance or result is "the degree to which a set of inherent characteristics fulfill requirements" (ISO 9000).

Grade as a design intent is a category assigned to deliverables having the same functional use but different technical characteristics.

Prevention is preferred over inspection. The cost of preventing mistakes is generally much less than the cost of correcting mistakes.

Differences in meaning of terms:

  • Prevention - keeping error out of he process. Inspection - keeping errors out of the hands of the customer.
  • Attribute sampling - the result either conforms or doesn't conform. Variable sampling - the result is rated on a continuous scale that measures the degree of conformity.
  • Tolerances - specified range of acceptable results. Control limits - identify the boundaries of common variation in a statistically stable process or process performance.

Cost of quality (COQ) includes all costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirements, and failing to meet requirements (rework).

Failure cost are the cost of poor quality and are

  • Internal - found by the project team;
  • External - found by the customer.

Levels of quality management:

  1. Let the customer to find the defects. Warranty issues, recalls, loss of reputation, rework costs.
  2. Detect and correct the defects before the deliverables are sent to the customer as part of the quality control process. Appraisal and internal failure costs.
  3. Use quality assurance to examine and designing of the project and products.
  4. Incorporate quality into the planning and designing of the project and product.
  5. Create a culture in the organization that is aware and committed to quality in processes and products.

Trends and Emerging Practices in Project Quality Management

  • Customer satisfaction. Understand, evaluate, define, manage requirements so that customer expectations are met. Conformance to requirements + fitness to use.
  • Continual improvement. Plan+Do+Check+Act (PDCA) cycle. Total Quality Management, Six Sigma, Lean Six Sigma.
  • Management responsibility.
  • Mutually beneficial partnership with suppliers. Win-Win.

Tailoring Considerations

  • Policy compliance and auditing. Policies, tools, techniques, templates.
  • Standards and regulatory compliance. Specific quality standards in the industry, governmental, legal, regulatory.
  • Continuous improvement. Organizational / project level.
  • Stakeholder engagement.

Considerations for Agile/Adaptive Environments

Recurring retrospectives regularly check on the effectiveness of the quality processes. Adjustment or drop.

Focus on small batches of work, incorporating as many elements of project deliverables as possible to uncover inconsistencies and quality issues earlier in the project life cycle.

понедельник, 3 февраля 2020 г.

7.4 Control Costs

The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.

Key benefit: the cost baseline is maintained throughout the project.

Frequency: throughout the project.

Process/ Asset GroupInputThe ProcessOutputProcess/ Asset Group
Project Management PlanCost management plan7.4 Control CostsWork performance information4.5 Monitor and Control Project Work
Cost baselineChange requests4.6 Perform Integrated Change Management Control
Performance measurement baselineCost management planProject Management Plan
Project DocumentsLesson learned registerCost baseline
7.3 Determine BudgetProject funding requirementsPerformance Measurement baseline
4.3 Direct and Manage Project Work Work performance dataCost forecastsProject Documents
Enterprise/ OrganizationOrganizational Process AssetsAssumption log
Basis of estimate
Cost Estimates
Lesson learned register
Risk register

Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures.

Cost control includes:

  • Influencing the factors that create changes to the authorized cost baseline.
  • Ensuring that all change requests are acted on in a timely manner.
  • Managing the actual changes when and as they occur.
  • Ensuring that cost expenditures do not exceed the authorized funding by period, by WBS component, by activity, and in total for the project.
  • Monitoring cost performance to isolate and understand variances from the approved cost baseline.
  • Monitoring work performance against funds expended.
  • Preventing unapproved changes from being included in the reported cost or resource usage.
  • Informing appropriate stakeholders of all approved changes and associated cost.
  • Bringing expected cost overruns within acceptable limits.

7.4.1 Inputs


7.4.1.1 Project Management Plan


Includes:

  • Cost management plan. How the project costs will be managed and controlled.
  • Cost baseline. The cost baseline is compared with actual results for change, correction action, preventive action.
  • Performance measurement baseline. For EVA.

7.4.1.2 Project Documents


Lesson learned register.

7.4.1.3 Project Funding Requirements


Projected expenditures plus anticipated liabilities.

7.4.1.4 Work Performance Data


Data on project status such as which cost have been authorized, incurred, invoiced, and paid.

7.4.1.5 Organizational Process Assets


Include:

  • Existing formal and informal cost control-related policies, procedures, guidelines.
  • Cost control tools.
  • Monitoring and reporting methods to be used.

7.4.2 Tools and Techniques


7.4.2.1 Expert Judgement


  • Variance analysis.
  • Earned value analysis.
  • Forecasting.
  • Financial analysis.

7.4.2.2 Data Analysis


  • Earned value analysis (EVA). Compares the performance measurement baseline to the actual schedule and cost performance, so we have three dimensions:
    • Planned value PV. Authorized budget assigned to scheduled work, not including management reserve. The total of the PV is also referred as the performance measurement baseline (PMB). The total planned value for the project is also known as budget at completion (BAC).
    • Earned value EV. A measure of work performed expressed in terms of the budget authorized for that work. It is often used to calculate the percent complete of a project. Progress measurement criteria should be established for each WBS component to measure work in progress.
    • Actual cost. It is the realized cost incurred for the work performed on an activity during a specific time period. It needs to correspond in definition to what was budgeted in the PV and measured in the EV.
  • Variance analysis.
    • Identify cost, schedule, completion variances.
    • Cost performance measurements are used to assess the value of variation.
    • Define are corrective actions are needed.
    • Analyse the cause of variances.
    • Schedule variance: SV=EV-PV.
    • Cost variance: CV = EV - AC.
    • Schedule performance index. It measures schedule efficiency: SPI = EV/PV.
    • Cost performance index. It measures the cost efficiency of budgeted resources: CPI = EA / AC.
  • Trend analysis. Graphical analysis.


  • Forecasting. Estimate at completion. If it becomes obvious that the BAC is no longer viable the EAC can be forecasted. It is typically based on the actual costs incurred for work completed + estimate to complete (ETC) the remaining work.
    • EAC forecast for ETC work performed at the budgeted rate. Took current performance by the actual costs -> ETC will be accomplished at the budgeted rate. EAC = AC + (BAC - EV).
    • EAC forecast for ETC work performed at the present CPI. EAC = BAC / CPI
    • EAC forecast for ETC work considering both SPI and CPI factors. EAC = AC+[(BAC-EV)/(CPI*SPI)]
  • Reserve analysis. To monitor the status of contingency and management reserves for the project to determine if these reserves are still needed or if additional reserves need to be requested. Risk analysis is also used.

7.4.2.3 To-Complete Performance Index


TCPI is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal: the ratio of the cost to finish the outstanding work to the remaining budget. (BAC-EV)/(BAC-AC).


7.4.3 Outputs


7.4.3.1 Work Performance Information


Includes information on how the project work is performing compared to the cost baseline.

7.4.3.2 Cost Forecast


Either a calculated EAC value or a bottom-up EAC value is documented and communicated to stakeholders.

7.4.3.3 Change Requests


To the cost and schedule baselines or other components of the project management plan.

7.4.3.4 Project Management Plan Updates


All updates are going through change control process. Components:

  • Cost management plan. Changes to control threshholds or specified levels of accuracy required.
  • Cost baseline. Changes in response to approved changes in scope, resources, or cost estimates.
  • Performance measurement baseline.

7.4.3.5 Project Documents Updates


Include:

  • Assumption log. The need to revise the resource productivity or others...
  • Basis of estimates.
  • Cost estimates.
  • Lesson learned register.
  • Risk register.

Earned Value Chart and Calculations

Estimating task or project status very difficult.

Budgeted expenditures or baseline expenditures.

Earned value of work performed - value completed.

There are several conventions to aid in estimating percent completion:

  • 50/50 rule. 50% completion is assumed when the task is begun, remaining 50% - when the work is complete. It is excessively generous for the task beginning and conservative toward the end of the task.
  • 0/100 rule. Very conservative rule. The project always seems to be running late. The earned value line will always lag the planned value line.
  • Critical input use rule. Task progress is defined by the amount of a critical inputs. Amount of poured concrete cubic meters -> status of the task of building the foundation.
  • The proportionality rule. Uses time or cost as the critical input.

The before mentioned variants can be applied to tasks not to the project itself. It the project include a lot of tasks then any of the variant applied is good enough.

The concept of earned value balances planned (baseline) cost, actual cost, schedule.

  • Budget at Completion (BAC).
  • Estimated cost at completion (EAC).


Cost (spending) variance (CV): EV - AC. Or money budgeted to accomplish the work done on current point of time minus actual cost of this work.

The schedule variance (SV) = EV - PV. Or budgeted money for the work done minus budgeted money to be spend on the work to be done on the current time.

The time variance (TV) = ST - AT. Or planned time minus actual time.

Variances can be calculated as ratios or indexes.

Cost Performance Index (CPI) = EV/AC

Schedule Performance Index (SPI) = EV/PV

Time Performance Index (TPI) = ST/AT. It is useful when an organization wishes to compare the performance of several projects. But be careful on the degree of accuracy of calculation of percent complete.

Example:

On current moment the work is expected to be costed as of 1500. The actual expenses are 1350. The completion percent = 67%.


Variances:

Cost Variance = EV - AC = 1500 * .67 - 1350 = - 350

Schedule Variance = EV - PV = 1500 * 0.67 - 1500 = -500.

Cost performance index CPI = EV / AC = 1500*0.67/1350 = 0.74

SPI = EV / PV = 1500 * 0.67 / 1500 = 0.67.

Time scheduled ST = AT * EV / PV.

Time variance TV = AT * (SPI - 1)

Cost Schedule Index CSI = CPI * SPI = EV ^ 2/ AC / PV.


If the project will continue with current rate of expenses then

Estimated cost to complete ETC = (BAC - EV) / CPI = (1500 - 1000) / 0.74 = 676

Estimated cost at completion EAC = ETC + AC = 676 + 1000 = 2026

пятница, 24 января 2020 г.

7.3 Determining Budget

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

Key benefit: it determines the cost baseline against which project performance can be monitored and controlled.

Frequency: once or at predefined points in the project.

A project budget includes all the funds authorized to execute the project.

The cost baseline is the approved version of the time-phased project budget that includes contingency reserves minus management reserves.


Process/ Asset GroupInputThe processOutputProcess/ Asset Group
Project Management PlanCost management plan7.3 Determine BudgetCost baselineProject Management Plan
Resource Management PlanProject funding requirements7.4 Control Costs
Scope baselineCost estimatesProject documents
Project DocumentsBasis of estimatesProject Schedule
Cost estimateRisk register
Project Schedule
Risk register
Business Documents Business case
Benefit management plan
12.2 Conduct ProcurementsAgreements
Enterprise/ OrganizationEnterprise environment factors
Organizational process assets

7.3.1 Inputs


7.3.1.1 Project Management Plan


Includes:

  • Cost management plan. How the project costs will be structured in the budget.
  • Resource management plan. Rates on resources, overheads, other foreseen costs.
  • Scope baseline. The project scope statement, WBS, WBS dictionary.

7.3.1.2 Project Documents


Include:

  • Basis of estimates.
  • Cost estimates.
  • Project schedule. Planned start/finish dates, milestones, work packages, control accounts -> aggregate costs to the calendar periods.
  • Risk register. How to aggregate the risk response costs.

7.3.1.3 Business Documents


  • Business case. The critical success factors.
  • Benefits management plan. Target benefits, timeframe for them, metrics.

7.3.1.4 Agreements


Cost related information.

7.3.1.5 Enterprise Environment Factors


Exchange rates.

7.3.1.6 Organizational Process Assets


Includes:

  • Existing formal/informal cost budgeting-related policies, procedures, guidelines;
  • Historical information and lesson learned repo;
  • Cost budgeting tools;
  • Reporting methods.

7.3.2 Tools and Techniques


7.3.2.1 Expert Judgement


Topics:

  • Previous similar projects;
  • Financial disciplines;
  • Funding requirements and sources.

7.3.2.2 Cost Aggregation


Aggregation in accordance with the WBS -> control accounts -> entire project.

7.3.2.3 Data Analysis


Reserve analysis -> management reserves for the project: an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project, for unknown unknowns. It is not includes into the cost baseline but is a part of the budget. If the reserve is used the amount is included into the baseline through change control project.

7.3.2.4 Historical Information Review


For parameters (project characteristics) or analogous estimates. Regression models. Used when:

  • Historical information is accurate;
  • Data are quantifiable;
  • Model is scale-able.

7.3.2.5 Funding Limit Reconciliation


The expenditure are under funding limits. Variances -> rescheduling of work -> out the rate of expenditure (?).

7.3.2.6 Financing


Funding methods for external financing. It can add additional requirements to the project.

7.3.3 Outputs


7.3.3.1 Cost Baseline


Approved version of the time-phased project budget, excluding management reserves. It is used as a basis to compare with actual results.



7.3.3.2 Project Funding Requirements


Total and periodic are from the cost baseline.

7.3.3.3 Project Documents Updates


  • Cost estimates.
  • Project schedule.
  • Risk register.